Delay of over 4 years pushes up bullet train project cost by 83%
NEW DELHI: A delay of over four years has pushed up the cost of the country’s first Bullet Train project by around 83% to Rs 1.98 lakh crore. The first leg of the project, between Surat and Bilimora, is scheduled to be inaugurated in Aug 2027, while the entire 508-km corridor is likely to be completed by Dec 2029.
Responding to a question on the cost escalation for the Ahmedabad-Mumbai High Speed Rail Corridor project being implemented by NHRSCL, at a briefing on govt’s Pragati initiative, Railway Board CEO and chairman Satish Kumar said, “While the final sanction for the revised cost is yet to be taken, it’s around Rs 1.98 lakh crore. It’s still under revision... It will be finalised within a month or two.”
Initially, the project was sanctioned at a cost of around Rs 1.1 lakh crore. The project has faced time and cost overruns due to different reasons, including delay in land acquisition, statutory clearances and finalisation of the rolling stock (trains).
In a statement last week, railways said that overall physical progress in the project stood at 55.6% until Nov 30 and financial progress at 69.6%. Until Nov end, Rs 85,801 crore had been spent on the project. TOI has learnt that PM Narendra Modi, while reviewing work of railway ministry last month, had directed it to expedite completion of the project.
Earlier on Friday, railway minister Ashwini Vaishnaw virtually witnessed from Rail Bhawan the final breakthrough in a 1.5-km-long mountain tunnel, a part of the project, in Maharashtra’s Palghar district. “A big milestone has been achieved today (Friday). This achievement is the breakthrough of the mountain tunnel 5,” he said.
In an official release, the ministry said that it is among the longest in Palghar district, being located between the Virar and Boisar bullet train stations. “It is the second tunnel breakthrough in Maharashtra, as the first 5-km-long underground tunnel between Thane and BKC was completed in Sept 2025,” it said. The project passing through Gujarat, Maharashtra, and Dadra and Nagar Haveli is designed to operate bullet trains at a speed of 320 kmph.
The corridor will also be fit for operating the advanced Japanese E10 series Shinkansen trains as it is being designed to allow trains to run at 20 kmph higher speed. Once completed, the corridor will lead to an estimated reduction of nearly 95% in carbon dioxide emissions compared to road transport.
Follow the latest election results 2026, live updates, winner lists, constituency-wise results, party-wise trends and full coverage for Tamil Nadu election results, West Bengal election results, Kerala election results, Assam election results and Puducherry election results results on Times of India.
Election Results 2026
Initially, the project was sanctioned at a cost of around Rs 1.1 lakh crore. The project has faced time and cost overruns due to different reasons, including delay in land acquisition, statutory clearances and finalisation of the rolling stock (trains).
In a statement last week, railways said that overall physical progress in the project stood at 55.6% until Nov 30 and financial progress at 69.6%. Until Nov end, Rs 85,801 crore had been spent on the project. TOI has learnt that PM Narendra Modi, while reviewing work of railway ministry last month, had directed it to expedite completion of the project.
Earlier on Friday, railway minister Ashwini Vaishnaw virtually witnessed from Rail Bhawan the final breakthrough in a 1.5-km-long mountain tunnel, a part of the project, in Maharashtra’s Palghar district. “A big milestone has been achieved today (Friday). This achievement is the breakthrough of the mountain tunnel 5,” he said.
In an official release, the ministry said that it is among the longest in Palghar district, being located between the Virar and Boisar bullet train stations. “It is the second tunnel breakthrough in Maharashtra, as the first 5-km-long underground tunnel between Thane and BKC was completed in Sept 2025,” it said. The project passing through Gujarat, Maharashtra, and Dadra and Nagar Haveli is designed to operate bullet trains at a speed of 320 kmph.
The corridor will also be fit for operating the advanced Japanese E10 series Shinkansen trains as it is being designed to allow trains to run at 20 kmph higher speed. Once completed, the corridor will lead to an estimated reduction of nearly 95% in carbon dioxide emissions compared to road transport.
Follow the latest election results 2026, live updates, winner lists, constituency-wise results, party-wise trends and full coverage for Tamil Nadu election results, West Bengal election results, Kerala election results, Assam election results and Puducherry election results results on Times of India.
Top Comment
S
Sanjiv
119 days ago
That means inflation in India has gone up by 83%Read allPost comment
Popular from India
- Tamil Nadu election result 2026: Date, time and where to follow live counting of votes - full schedule
- West Bengal election result 2026: Date, time and where to follow live counting of votes - full schedule
- India dismisses Nepal’s Kailash yatra objection over Lipulekh Pass
- SG Tushar Mehta takes swipe at ‘bully’ judges in his book
- Assembly election result 2026: Date and time of result for Assam, Kerala, Tamil Nadu, West Bengal, Puducherry, exit poll predictions, where, how to watch and other details
end of article
Trending Stories
- Election Results 2026 Live Updates: Bengal, Tamil Nadu, Assam, Kerala, Puducherry brace for voters' verdict
- NEET UG 2026: Safe score, expected cut-off and marks needed for MBBS admission to government and private colleges
- Assembly election result 2026: Date and time of result for Assam, Kerala, Tamil Nadu, West Bengal, Puducherry, exit poll predictions, where and how to watch and other details
- US-Israel-Iran War News Live Updates: Iranian super tanker slips past US blockade with $220 million oil cargo
- CBSE Class 12th Result Live Updates: When will class 12 scorecards be released? Check latest updates, steps to download from DigiLocker and UMANG app here
- Luka Doncic injury update: Brian Windhorst drops latest news on Lakers star
- Maharashtra HSC Result 2026 Live Updates: Expected next week after Buddha Purnima and weekend gap, DigiLocker shows coming soon status
Featured in India
- Congress: Government ignored Nicobar concerns
- Heart donated in Panchkula gives Sudanese teen in Delhi new life
- Abandoned in forest, 2-year-old walks for 20 hours, survives
- Team Raghav Chadha to get audience with President Murmu ahead of Bhagwant Mann
- Canadian intelligence agency accuses India of interference, spying
- India dismisses Nepal’s Kailash yatra objection over Lipulekh Pass
Photostories
- Morning affirmation at 5 am: Thoughts that hit different when the world is still asleep
- You’re brushing your teeth wrong: What dentist says most people miss
- How to make Pudina Paratha for summer breakfast
- 5 Bengali breads every foodie should try
- 5 phases every marriage quietly moves through- And how to deal with them
- 5 rare watches from Sachin Tendulkar’s collection you should know
- You’re walking, but not like this: How interval walking improves fitness naturally
- Subtle signs you might be vitamin D deficient, and what your body is trying to tell you
- Red vs green Apple: How to choose the right one for your health goals
- Rihanna to Katy Perry: 7 most bizarre Met Gala looks that stole the spotlight
Videos
03:40 Nepal Objects To India-China Plan To Conduct Kailash Mansarovar Yatra Via Lipulekh03:25 India-Linked LPG Tanker MT Sarv Shakti Heads To Visakhapatnam After Crossing Hormuz03:01 Passenger Opens Emergency Exit Door On Air Arabia Flight While Taxiing At Chennai Airport, Arrested- Ahead Of Counting, Gunmen Open Fire At BJP Leader’s House In Bengal’s Noapara
- ‘I Am Also A Victim’: Vinesh Phogat Identifies As Complainant In Brij Bhushan Sexual Harassment Case
03:01 BJP MP Sandeep Pathak Claims ‘No Information’ On FIRs, Alleges Misuse Of State Machinery In Punjab04:30 Indian Startup Launches Mission Drishti, World’s First OptoSAR Satellite, Aboard SpaceX Falcon 904:15 Diljit Dosanjh Confronts Khalistan Supporters at Calgary Concert, Explains KBC Appearance03:21 Delhi Approves ₹48,000 Crore Metro Expansion Plan To Connect Outer Regions With City Core
Up Next