After five missed deadlines for entire Hinjewadi-Shivajinagar Metro corridor, even phased opening faces delays
Pune: Commuters already grappling with rising fuel costs and daily traffic congestion are set for fresh disappointment over the Hinjewadi-Shivajinagar Metro. After missing five deadlines for completing the entire corridor, even the phased rollout has slipped. The Maan-Balewadi stretch, earlier expected to open by June-end, is now unlikely to be operational before July.
Back in March, chief minister Devendra Fadnavis had announced that the 23km elevated corridor would open in two stages — the first in May, followed by the second in July. But May came and went. The first phase was then pushed to June-end. Now, even that deadline is set to quietly slip.
Officials said the project concessionaire had aimed to make the first 12 stations operational by June-end. Senior PMRDA officials, however, indicated that commercial services would only begin after a formal inauguration — likely in July. “The launch could happen in the first half of July or slightly later, depending on the inauguration schedule,” an official admitted, underscoring the uncertainty still hanging over the project.
For thousands of commuters battling daily gridlock and spiralling fuel costs, the delay in phased opening feels like déjà vu. Anita D, an IT professional who continues to rely on her private vehicle, voiced a sentiment echoed across the IT hub. “The wait has been unending. There is a new deadline almost every month,” she said, reflecting the growing frustration among commuters to the IT hub.
Priya P, who travels daily from Baner to Hinjewadi by autorickshaw, questioned the need for ceremonial delays. “With rising fuel prices and shortages, govt should prioritise starting operations immediately. Formal inaugurations are not what people need right now,” she said.
Other commuters pointed to the shifting goalposts. Mohit Pawar said the original plan was to open the entire stretch in one go. “Now it’s split into 12 stations and later 11. Given the fuel crisis and traffic chaos, it should have been operational much earlier. It would have made a real difference,” he said.
Despite the setbacks, the officials maintained that the project was nearing completion. The Metro Line 3 corridor is 95.2% ready, an official said, adding that the first phase was pending mandatory safety clearances. “The Commissioner of Metro Rail Safety (CMRS) is expected to inspect the corridor on June 10. Final approval, however, could stretch beyond June, possibly pushing operations further into July. A decision will be taken after inspection, but the process may extend till end-June or even July,” a senior PMRDA official said.
Meanwhile, not all stations are fully ready. Authorities conceded that work was still pending at a few stops, raising the possibility of further delays in parts of the corridor. The remaining stretch is expected to be completed over the next three to four months.
Once operational, the Metro Line 3 is expected to drastically cut travel time between Pune city and the Rajiv Gandhi Infotech Park — one of India’s busiest IT hubs. It will also integrate with the existing Pune Metro network, connecting the PCMC-Swargate and Vanaz-Ramwadi lines.
But for now, that promise remains just out of reach, as commuters continue to wait, watch and hope that this time, the deadline finally holds.
Officials said the project concessionaire had aimed to make the first 12 stations operational by June-end. Senior PMRDA officials, however, indicated that commercial services would only begin after a formal inauguration — likely in July. “The launch could happen in the first half of July or slightly later, depending on the inauguration schedule,” an official admitted, underscoring the uncertainty still hanging over the project.
For thousands of commuters battling daily gridlock and spiralling fuel costs, the delay in phased opening feels like déjà vu. Anita D, an IT professional who continues to rely on her private vehicle, voiced a sentiment echoed across the IT hub. “The wait has been unending. There is a new deadline almost every month,” she said, reflecting the growing frustration among commuters to the IT hub.
Priya P, who travels daily from Baner to Hinjewadi by autorickshaw, questioned the need for ceremonial delays. “With rising fuel prices and shortages, govt should prioritise starting operations immediately. Formal inaugurations are not what people need right now,” she said.
Other commuters pointed to the shifting goalposts. Mohit Pawar said the original plan was to open the entire stretch in one go. “Now it’s split into 12 stations and later 11. Given the fuel crisis and traffic chaos, it should have been operational much earlier. It would have made a real difference,” he said.
Despite the setbacks, the officials maintained that the project was nearing completion. The Metro Line 3 corridor is 95.2% ready, an official said, adding that the first phase was pending mandatory safety clearances. “The Commissioner of Metro Rail Safety (CMRS) is expected to inspect the corridor on June 10. Final approval, however, could stretch beyond June, possibly pushing operations further into July. A decision will be taken after inspection, but the process may extend till end-June or even July,” a senior PMRDA official said.
Once operational, the Metro Line 3 is expected to drastically cut travel time between Pune city and the Rajiv Gandhi Infotech Park — one of India’s busiest IT hubs. It will also integrate with the existing Pune Metro network, connecting the PCMC-Swargate and Vanaz-Ramwadi lines.
But for now, that promise remains just out of reach, as commuters continue to wait, watch and hope that this time, the deadline finally holds.
You Can Also Check: Gold Rate in Pune | Silver Rate in Pune | Bank Holidays in Pune | Public Holidays in Pune | Petrol Price in Pune | Diesel Price in Pune | CNG Price in Pune | LPG Price in Pune
Comments
Be the first to share a thought and become theFirst Voiceof this News Article
end of article
In Pune
- Three held in Kondhwa for stealing 17 goats two days before Bakrid
- Asha workers on census duty brave heat, glitches
- PMRDA plans new link roads, widening projects to decongest Hinjewadi IT hub
- MACT orders Rs 19.2L compensation in teenager’s accidental death case
- PMC sends notice to hospital on newborn’s death after C-section
- Delivery person held in nursing job scam, third suspect in net
- MNGL hikes CNG price by Rs 2.50 in Pune; 1kg to now go up to Rs 94.75
Featured In City
- Is Congress repeating the ‘Veerendra Patil mistake’ with Ahinda votes?
- Rain risk: 890 trees shadow Bengaluru Metro tracks, 100 too close for comfort
- Maharashtra FDA conducts raids across cities, seizes banned and adulterated items worth Rs 40 lakh; 33 arrested for selling gutka
- Legislative Privilege Explained: Advocates Debate Whether Remarks Made In The Assembly Lose Immunity Outside
- A calm goodbye from state’s most combative socialist
- Am going nowhere, will stay active, says Siddaramaiah
- Despite higher detection rates, multiple sclerosis awareness remains low in India
Photostories
- 5 art villages of india where art has been passed down from generations and is a way of life
- 2 Misunderstood traits of high intelligence
- Can diabetics eat mangoes? Experts say yes, but only if you follow these rules
- Who is Pankaj Bhadouria? Celebrity Chef and MasterChef India season 1 Winner diagnosed with breast cancer
- 5 lesser-visited UNESCO World Heritage Sites in India travellers should explore
- Why beauty buyers are spending more on body care than skincare
- Otters are closely related to wolverines: 7 facts that will surprise you
- International Day of Action for Women's Health: History and Significance
- King Cobra can do THIS? 9 shocking facts about the deadly snake
- 10 refreshing and high-protein sattu recipes to cool the gut during summer season
Videos
02:59 Patna Builder Gifts CM Portrait, Internet Reacts With “Majnu Bhai Would Be Proud” Jokes03:01 Tension At West Bengal Border As Migrants Wait For Return Amid Holding Centre Operations03:04 Twisha Sharma Death Case: CBI Arrests Mother-In-Law & Retired Judge Giribala Singh06:10 From Brazil To India: Inside Gujarat’s Biggest Cocaine Seizure03:32 Siddaramaiah Resigns As Karnataka CM, DK Shivakumar Likely To Take Over03:27 Special Eid-ul-Adha Namaz Held At Taj Mahal Amid Tight Security Across Uttar Pradesh Cities03:24 Tamil Nadu CM Vijay Postpones Delhi Meeting With Rahul Gandhi After PM Modi Meet04:00 Priyanka Gandhi Intervention Boosts DK Shivakumar’s Push For Karnataka Chief Minister Post: Report03:04 TMC MP Kakoli Ghosh Dastidar Accuses Colleague Kalyan Banerjee Of Misogyny And Verbal Abuse
Top Trends
Up Next
Follow Us On Social Media