Railway ministry blames land acquisition hurdles for delays in Bengal projects
KOLKATA: The ministry of railways has reported significant delays in several railway infrastructure projects across West Bengal, primarily due to challenges in land acquisition, an official statement said. Despite a substantial increase in funding, with allocations rising three times from Rs 4,380 crore during 2009-14 to Rs 13,941 crore in 2024-25, the pace of project execution remains hindered, the ministry statement said.
As of April 1, 2024, there are 43 railway projects in West Bengal, encompassing 4,479 km and costing Rs 60,168 crore. These projects, which fall fully or partly within West Bengal under the Eastern, South Eastern, and North East Frontier Railways, involve new lines and modernisation efforts.
Of these, 1,655 km have been commissioned, with a capex outgo of Rs 20,434 crore up to March 2024.
The ministry stated that acquisition remains a significant bottleneck as out of the total 3,040 hectares required, only 640 hectares (21 per cent) have been acquired, leaving a balance of 2,400 hectares (79 per cent) yet to be secured.
It said the Railways acquires land for its projects through state governments.
Railways pointed out some key projects experiencing delays due to land acquisition issues include: Nabadwipghat-Nabadwipdham new line (10 km): requires 106.86 hectares; only 0.17 hectares acquired. Chandaneshwar-Jaleswar new line (41 km): requires 158 hectares; no land acquired to date. Naihati-Ranaghat third line (36 km): requires 87.83 hectares; only 0.09 hectares acquired. Balurghat-Hilli new line (30 km): requires 156.38 hectares; 67.38 hectares acquired. Bypasses at Sainthia (5 km) and Sitarampur (7 km): require 22.28 hectares; but only 2.22 hectares could be acquired.
The completion of railway projects depends on various factors, including prompt land acquisition by state governments, forest clearances, cost-sharing deposits, shifting of utilities, statutory clearances, geological and topographical conditions, law and order situations, and climatic conditions affecting the number of working months available annually, the ministry said.
The ministry emphasises that while the government is prepared to execute these projects, their success heavily relies on the support and cooperation of the West Bengal government in expediting land acquisition processes, the statement said.
Railways said to address these challenges, the ministry has implemented measures such as establishing Gati Shakti units, prioritising projects, increasing fund allocations for priority projects, delegating powers at the field level, closely monitoring progress, and regularly coordinating with state governments and relevant authorities to expedite land acquisition and clearances.
Stay updated with the latest news on Times of India. Don't miss daily games like Crossword, Sudoku, and Mini Crossword.
Of these, 1,655 km have been commissioned, with a capex outgo of Rs 20,434 crore up to March 2024.
The ministry stated that acquisition remains a significant bottleneck as out of the total 3,040 hectares required, only 640 hectares (21 per cent) have been acquired, leaving a balance of 2,400 hectares (79 per cent) yet to be secured.
It said the Railways acquires land for its projects through state governments.
Railways pointed out some key projects experiencing delays due to land acquisition issues include: Nabadwipghat-Nabadwipdham new line (10 km): requires 106.86 hectares; only 0.17 hectares acquired. Chandaneshwar-Jaleswar new line (41 km): requires 158 hectares; no land acquired to date. Naihati-Ranaghat third line (36 km): requires 87.83 hectares; only 0.09 hectares acquired. Balurghat-Hilli new line (30 km): requires 156.38 hectares; 67.38 hectares acquired. Bypasses at Sainthia (5 km) and Sitarampur (7 km): require 22.28 hectares; but only 2.22 hectares could be acquired.
The completion of railway projects depends on various factors, including prompt land acquisition by state governments, forest clearances, cost-sharing deposits, shifting of utilities, statutory clearances, geological and topographical conditions, law and order situations, and climatic conditions affecting the number of working months available annually, the ministry said.
Railways said to address these challenges, the ministry has implemented measures such as establishing Gati Shakti units, prioritising projects, increasing fund allocations for priority projects, delegating powers at the field level, closely monitoring progress, and regularly coordinating with state governments and relevant authorities to expedite land acquisition and clearances.
Stay updated with the latest news on Times of India. Don't miss daily games like Crossword, Sudoku, and Mini Crossword.
Popular from India
- Priyanka Gandhi bristles as BJP MP gifts her 'Sikh genocide' bag
- 52 kg gold, Rs 10 crore cash seized by IT linked to Lokayukta raid on ex-RTO constable and associate
- Jaipur highway tanker collision death toll reaches 14, over 28 injured
- 'Our recollections differ': Shashi Tharoor, Hardeep Puri in war of words over 2009 dinner with George Soros in US
- Rs 2.5 crore cash, other assets found in constable house
end of article
Trending Stories
- Rs 2.5 crore cash, other assets found in constable house
- 8 reasons smart students prefer mind maps over notes
- Luigi Mangione's motive revealed: Plan made in August as 'UnitedHealthcare checks every box'
- White House in crisis? Biden and Harris 'cancel Christmas trips and rush back' amid speculations of emergency
- Why was Stonehenge built? Scientists finally solve 5,000-year-old mystery
- Fire engulfs at Hyderabad's Sattva Knowledge City, no casualties reported
- Who is Taleb? Car driver behind Germany's Christmas market attack
Visual Stories
- 10 beautiful animals that are pink in colour
- 9 vegetarian dishes shine in the ‘100 Best Dishes in the World’ list
- How to grow Spring Onion in the kitchen garden without soil (you only need water!)
- How to make nutrition-rich and super delicious Bathua Paneer Paratha
- 10 best places to visit in North India for a thrilling wildlife experience
UP NEXT
Start a Conversation
Post comment