Solar projects in Raj worth ₹2k cr stalled amid policy uncertainties
Jaipur: After orders for production curtailment, solar power developers in the state are now being denied permission to commission projects worth Rs 2,000 crore (500MW) due to policy ambiguities surrounding Battery Energy Storage Systems (BESS).
Industry stakeholders said the state energy department’s rules for mandatory battery storage alongside solar plants are being interpreted negatively to hold back approvals.
As per the policy rolled out about six months ago, solar developers setting up plants for companies to sell power were given 15 months to install mandatory battery storage up to 25% of plant capacity.
Despite this timeline, approvals required for power supply – including commissioning clearances, long-term open access agreements and wheeling and banking arrangements (WBA) – have been withheld by discoms and the Prasaran Nigam.
“Despite being technically ready, projects are unable to begin operations due to the absence of final approvals and take-off clearances,” said Nitin Agarwal, CEO of Rajasthan Solar Association (RSA).
Expressing disappointment, Agarwal said the lack of a clear standard operating procedure (SOP) and inconsistent interpretation of regulations by different arms of the govt have created stifling bottlenecks.
In a recent meeting held to find a way out and save affected projects, solar industry representatives said govt authorities are insisting that BESS be installed before solar commissioning, even though a 15-month grace window is allowed.
Citing examples, Arun Mahla, RSA vice president and director of Stockwell Solar Services, said even those projects that have already set up both solar plants and BESS units are being denied permission to start operations. “There is no standard operating procedure in place even for those who have set up battery systems,” said Mahla.
Industry insiders also flagged difficulties in sourcing raw material for battery storage due to ongoing tensions in the Gulf region.
The financial implications resulting from these issues are severe. Many developers financed their projects through bank loans, anticipating timely commissioning and revenue generation. With projects unable to supply power, however, cash flows have dried up, making it difficult to service debt.
“If the situation persists, several developers risk being classified as non-performing or default entities, which could restrict their ability to secure financing for future projects,” said RSA’s Agarwal.
During the Resurgent Rajasthan summit, the state govt signed MoUs worth 35 lakh crore, with projects worth Rs 28 lakh in the power sector alone. Policy flip-flops since then are expected to have a telling impact if investors feel their investments are not safe in the state.
GFX
Hitting Investor Confidence
Policy ambiguity around mandatory Battery Energy Storage Systems hits solar projects
State energy dept rules require up to 25% battery storage capacity of solar plants within 15 months
Despite this grace period, approvals for commissioning, open access and wheeling are being withheld
Industry stakeholders blame the absence of a clear SOP and inconsistent interpretation of rules
Authorities insist on installing BESS before solar commissioning, contradicting a 15-month grace window
Even projects that have already set up both solar and BESS units are denied permissions due to procedural gaps
Financial stress is mounting as developers struggle to service bank loans without revenue from power supply
Get real-time updates and result insights on the UBSE UK Board Results 2026 and CBSE 12th Result 2026
As per the policy rolled out about six months ago, solar developers setting up plants for companies to sell power were given 15 months to install mandatory battery storage up to 25% of plant capacity.
Despite this timeline, approvals required for power supply – including commissioning clearances, long-term open access agreements and wheeling and banking arrangements (WBA) – have been withheld by discoms and the Prasaran Nigam.
“Despite being technically ready, projects are unable to begin operations due to the absence of final approvals and take-off clearances,” said Nitin Agarwal, CEO of Rajasthan Solar Association (RSA).
Expressing disappointment, Agarwal said the lack of a clear standard operating procedure (SOP) and inconsistent interpretation of regulations by different arms of the govt have created stifling bottlenecks.
In a recent meeting held to find a way out and save affected projects, solar industry representatives said govt authorities are insisting that BESS be installed before solar commissioning, even though a 15-month grace window is allowed.
Industry insiders also flagged difficulties in sourcing raw material for battery storage due to ongoing tensions in the Gulf region.
The financial implications resulting from these issues are severe. Many developers financed their projects through bank loans, anticipating timely commissioning and revenue generation. With projects unable to supply power, however, cash flows have dried up, making it difficult to service debt.
“If the situation persists, several developers risk being classified as non-performing or default entities, which could restrict their ability to secure financing for future projects,” said RSA’s Agarwal.
During the Resurgent Rajasthan summit, the state govt signed MoUs worth 35 lakh crore, with projects worth Rs 28 lakh in the power sector alone. Policy flip-flops since then are expected to have a telling impact if investors feel their investments are not safe in the state.
GFX
Hitting Investor Confidence
Policy ambiguity around mandatory Battery Energy Storage Systems hits solar projects
State energy dept rules require up to 25% battery storage capacity of solar plants within 15 months
Despite this grace period, approvals for commissioning, open access and wheeling are being withheld
Industry stakeholders blame the absence of a clear SOP and inconsistent interpretation of rules
Authorities insist on installing BESS before solar commissioning, contradicting a 15-month grace window
Even projects that have already set up both solar and BESS units are denied permissions due to procedural gaps
Financial stress is mounting as developers struggle to service bank loans without revenue from power supply
You Can Also Check: Gold Rate in Jaipur | Silver Rate in Jaipur | Bank Holidays in Jaipur | Public Holidays in Jaipur | Jaipur AQI | Weather in Jaipur
Get real-time updates and result insights on the UBSE UK Board Results 2026 and CBSE 12th Result 2026
Popular from City
- No equipment in labs, no ACs in halls: MBBS students strike on campus
- Delhi rape-murder case: Accused made to retrace footsteps; 3-hour exercise to know how he entered, what he did
- 4 girlfriends, 'no feelings', 12-page death note: How Bengaluru-based techie allegedly drove fiance to suicide
- Delhi sizzles as mercury hits 42.8°C, hottest April day in 4 years
- Karnataka high court clears actor Ranveer Singh, asks him to visit deity in 4 weeks
end of article
Trending Stories
- Board Exam Results 2026 Live Updates: ICSE, ISC, AP and Telangana SSC results soon, Assam HS results on April 28
- US-Israel-Iran War Ceasefire News Live Updates: As Trump mulls strikes, Iran says 'list of targets ready', warns Saudi Arabia of retaliation
- Patrick Mahomes and Brittany Mahomes land a whopping $325 million valuation with off field move amid his recovery
- NEET Admit Card 2026 LIVE: NTA to issue hall tickets today for over 22 lakh candidates ahead of May 3 exam; how to download at neet.nta.nic.in
- IPL 2026: Karun Nair Left Devastated, On the Verge of Tears as PBKS Script Record Chase – Watch
- IPL 2026: Youngest. Fastest. Unstoppable! Vaibhav Sooryavanshi Scripts T20 History Yet Again
- FBI director Kash Patel 'likely' to be fired: 'It’s only a matter of time'
Featured in city
- Peak power demand at record high amid scorching heatwave in India
- Karnataka high court clears actor Ranveer Singh, asks him to visit deity in 4 weeks
- Delhi rape-murder case: Accused made to retrace footsteps; 3-hour exercise to know how he entered, what he did
- Dawood Ibrahim aide and drug kingpin Salim Dola detained in Istanbul
- Delhi sizzles as mercury hits 42.8°C, hottest April day in 4 years
- 'No clinching evidence': Man jailed for 12 years in Pocso case acquitted
Photostories
- Puffy eyes that won’t go away? Why it could signal kidney trouble, and when to get tested
- 8 surprising benefits of drinking lassi regularly in summers
- From not wanting to marry outside her religion to facing mistreatment by senior actors on TV sets: Reem Shaikh gets candid
- Bengaluru–Mumbai Vande Bharat Sleeper To Hit Tracks From August 1: All You Need To Know
- 7 yoga poses that people with high BP can do safely
- Heatwave sweeps cities: What to expect ahead?
- Interesting facts about cows: 10 surprising signs they’re smarter than you think
- Getting breathless after a short walk? Why more young adults are facing this silent warning sign
- Step inside S. Sreesanth’s crores worth Kochi bungalow: A multi-acre property defined by cricket journey, comebacks and family-first living
- 6 cooling foods Ayurveda recommends during extreme heat
Videos
04:12 BJP MP Ravi Kishan Alleges ‘Politics of Fear’ in WB, Claims Voters Rising Against Violence & Threats03:01 DRDO Unveils Next-Gen Armoured Platforms Designed For Multi-Terrain Combat And Rapid Deployment03:03 Rahul Gandhi Reacts to Cong Worker Killing in WB, Seeks Strict Action and Justice03:05 Engine Failure Forces Emergency Evacuation of Swiss Delhi-Zurich Flight; Six Injured- Manipur Govt Addresses COCOMI Demands After Protesters Clash With Police During March To CM'S House
03:37 PM Modi Condemns Shooting Near White House Dinner, Says ‘Violence Has No Place’05:45 Strait of Hormuz to US Elections: Ex-CJI Maps Shockwave of Global Interconnection15:08 Swati Maliwal Launches Fresh Attack On Kejriwal After BJP Switch Over ‘Rs 100 Cr House’03:02 Raghav Chadha Sees 1 Million Drop In Followers After BJP Move, Gen Z Reacts
Up Next
Start a Conversation
Post comment