Delay in utility shifting holds up Gurgaon metro work on Hero Honda Chowk link
Gurgaon: Construction on a 2.5km stretch of the new metro corridor between Umang Bhardwaj Chowk and Hero Honda Chowk has stalled due to delay in right of way (RoW) clearance and shifting utilities.The section is undergoing road redevelopment by NHAI, funded by GMDA, and forms part of the metro project's phase 1. A senior GMRL official said work cannot move forward until the land is cleared.
The problem was reviewed in a meeting on Friday involving GMRL, NHAI, and GMDA. GMRL officials said the land needed for construction has not been cleared and asked NHAI to share a firm timeline for RoW clearance and utility relocation so work can begin on the stretch.Multiple underground and overhead utilities, including water pipelines, sewer lines, and power lines, run along the corridor. In addition, a shop, a portion of Himgiri Ashram, and a CNG station fall in the metro corridor's alignment, further constraining space for construction.Metro officials said although metro infrastructure needs a limited working area, the spread of utility networks across the stretch makes relocation necessary before construction can start.An NHAI official said progress depends on Dakshin Haryana Bijli Vitran Nigam (DHBVN) shifting power infrastructure before key utility work can proceed."We have an interdependency on DHBVN for shifting of power poles along the stretch, particularly on the left-hand side. Until those poles are relocated, we cannot begin work on the water pipeline. Similarly, the sewer line work on the left-hand side is also held up due to this dependency. Once DHBVN completes its portion and the site is cleared, we will begin water and sewer line works, which we aim to complete within 3 months," the official said.The official added that relocation linked to Haryana Vidyut Prasaran Nigam Limited (HVPNL) substation is underway and will be completed by June."We are also planning to begin demolition of the boundary wall at Himgiri Ashram within the next 10 days," the official said.The delay has created a bottleneck in phase 1 of the 15.3km corridor connecting Millennium City Centre to Sector 9. While pile cap work and other foundational activities are progressing in other sections, the lack of clear RoW in this stretch continues to hold up construction.In August last year, Dilip Buildcon and Ranjit Buildcon were awarded the phase 1 construction contract for Rs 1,277 crore, with a completion timeline of 30 months.
The problem was reviewed in a meeting on Friday involving GMRL, NHAI, and GMDA. GMRL officials said the land needed for construction has not been cleared and asked NHAI to share a firm timeline for RoW clearance and utility relocation so work can begin on the stretch.Multiple underground and overhead utilities, including water pipelines, sewer lines, and power lines, run along the corridor. In addition, a shop, a portion of Himgiri Ashram, and a CNG station fall in the metro corridor's alignment, further constraining space for construction.Metro officials said although metro infrastructure needs a limited working area, the spread of utility networks across the stretch makes relocation necessary before construction can start.An NHAI official said progress depends on Dakshin Haryana Bijli Vitran Nigam (DHBVN) shifting power infrastructure before key utility work can proceed."We have an interdependency on DHBVN for shifting of power poles along the stretch, particularly on the left-hand side. Until those poles are relocated, we cannot begin work on the water pipeline. Similarly, the sewer line work on the left-hand side is also held up due to this dependency. Once DHBVN completes its portion and the site is cleared, we will begin water and sewer line works, which we aim to complete within 3 months," the official said.The official added that relocation linked to Haryana Vidyut Prasaran Nigam Limited (HVPNL) substation is underway and will be completed by June."We are also planning to begin demolition of the boundary wall at Himgiri Ashram within the next 10 days," the official said.The delay has created a bottleneck in phase 1 of the 15.3km corridor connecting Millennium City Centre to Sector 9. While pile cap work and other foundational activities are progressing in other sections, the lack of clear RoW in this stretch continues to hold up construction.In August last year, Dilip Buildcon and Ranjit Buildcon were awarded the phase 1 construction contract for Rs 1,277 crore, with a completion timeline of 30 months.
Popular from City
- Samajwadi Party leader dies after 1,000 kg lighting pole crashes on SUV in UP’s Pratapgarh
- Villages in Noida in grip of child-lifting rumours; parents quit jobs, change shifts: ‘We can’t take chances’
- US confirms death of Karnataka’s Saketh Sreenivasaiah; father says no official info yet
- Chhatrapati Shivaji Maharaj–Tipu Sultan row snowballs: BJP demands Harshawardhan Sapkal’s resignation, Congress silent
- Mumbai couple back from Thailand cheated of 1,000 Thai Baht; driver demanded cash mid-ride, 2 held
end of article
Trending Stories
- JEE Main 2026 Result Live Updates: Session 1 result expected to be released tomorrow, check latest updates here
- T20 WC LIVE: UAE give Afghans strong fight in Delhi
- 'Biggest crime in the world': Shoaib Akhtar slams PCB chief Mohsin Naqvi, Pakistan after India defeat
- Late-night drive, temple visit: Bengaluru car crash victims gave different reasons at home to step out
- JEE Main 2026 final answer key for session 1 released: Direct link here, result to be announced shortly
- Villages in Noida in grip of child-lifting rumours
- JEE Main 2026 session 1 expected to be declared today: Check details here
Featured in city
- Vaibhav Suryavanshi Opts Out: Rising Bihar star skips CBSE exams; cites cricket, security concerns
- Late-night drive, temple visit: Bengaluru car crash victims gave different reasons at home to step out
- Mumbai's Mulund concrete block collapse: MMRDA orders special intensive safety inspection across entire Metro 4 corridor
- Avoid 'young, attractive female' profiles: MHA SOP warns cops against Pakistani honeytraps
- Delhi skill push falters: 5 years after launch, seat closures and sharp drop in student intake
- Summer ready in Bengaluru? BWSSB lists 448 high-alert water-stressed zones; rolls out Rs 10 cr action plan
Photostories
- 2026 movie release dates: Every Marvel, Disney and Pixar blockbuster scheduled so far
- Top 5 real estate hotspots in Mumbai: A strategic investment guide for 2026
- Thomas Cruise Mapother IV: Tom Cruise’s journey from struggle to stardom
- Top 5 iconic fashion moments in Hollywood history that defined style forever
- 8 traditional Mughlai desserts that one should try in a lifetime
- 10 tiger reserves in India with exceptional sighting records
- What happens when you chant ‘Om’ daily for 21 days and the right way to do it
- 5 ways infrastructure projects raise nearby property values
- 7 vegetables which are perfect to sow in February
- 10 powerful baby names that mean 'shining like the sun'
Videos
04:45 'World Recognises India’s AI Power': Norway To New Zealand Praise India As AI Impact Summit Begins04:18 Amit Shah Calls 2014–2026 A Golden Era For India’s Internal Security, Vows Maoism Eradication04:23 Karnataka Minister Priyank Kharge Alleges Money Laundering By RSS, Questions Tax And Legal Status08:51 Congress In Damage Control Mode After Mani Shankar Aiyar’s Baton Remark To Kerala Chief Minister03:17 Alienating India Over BRICS Was Wrong, Says German Foreign Minister Wadephul At Munich Conference06:13 'Tremendous Alliance': Netanyahu Highlights India's Love For Israel Ahead Of PM Modi's Visit11:15 Indian Fans Celebrate As India Smashes Pakistan In T20 WC Clash, Pak Fans Voice Disappointment03:39 “From Compassion To Combat, Operation Sindoor Reflects New India” Rajnath Singh05:20 “Delhi Fully Prepared For AI Summit,” Says Kuljeet Chahal As NDMC Unveils Grand Illumination Drive
Up Next
Start a Conversation
Post comment