Panaji smart city seeks extension for sewerage works completion
Rodrigues said that work of laying the final stretch of the sewerage line remains to be completed, but he could not give a definite timeline for its completion.
He said that 90% of all the Smart City Mission works in the state capital have been completed and that he is satisfied with the quality of the work. He said that the contractors and engineers encountered a lot of hindrances and challenges while trying to complete the works.
Giving reporters an update on the pending works, Rodrigues said that of 200m of sewerage line that was pending, 170m was completed. He said that 30m remains to be laid, with work going on round the clock.
He said that borewells have been laid at Taad Maad to dewater the trenches, which are at a depth of 12m. He also said that work at Rua De Ourem could not be completed.
“We were supposed to complete Rua De Ourem, but again there was a problem because there was a pumping line that was supposed to come up. This pipeline was tendered by PWD three times, and there have been no takers. The concrete cannot be laid until the pipeline comes in,” said Rodrigues.
Despite these delays, Rodrigues insisted that the Smart City mission has not “missed any deadline”.
“Except for the Taad Maad stretch, we have completed every single sewerage work, every single road work as per the affidavit filed by the court. No road closure, open trenching, barricading is going on in Panaji, and if any such activity is seen, it is not of the Smart City Mission. Almost 90% of work has been completed in the city. I stand by the quality, and we have a five-year warranty,” said Rodrigues.
When asked about the inconvenience caused to motorists, Rodrigues said, “I don’t agree.”
‘Ribandar-Chorao ferry ramp complete’
“As far as the Ribandar ferry ramp is concerned, we have completed the ramp and clearing of debris is going on. We will hand over the ramp to the RND for the Ro-Ro service. We had to wait for the tides to be at the lowest to complete the work. The RND will have to run trials for the Ro-Ro ferry and they are waiting for the ferry to arrive,” said Rodrigues.
Popular from City
- Bareilly businessman collapses on stage, dies while dancing with wife on 25th anniversary
- 49kg gold, Rs 38.4 crore in hawala transfers: How Karnataka jeweller Sahil Jain helped actor Ranya Rao
- Punjabi songs, luxury bags and a Thar: How Punjab cop Amandeep Kaur mocked own force in viral reels despite 'ban'
- As MNS ups ante over Marathi, bank staff write to CM seeking protection
- Protests erupt in Kolkata and Ahmedabad against Waqf Amendment Bill
end of article
Trending Stories
- PSEB Punjab Board 8th Class Result 2025 Live Updates: Punjab board class 8th result announced on pseb.ac.in; pass percentage 97.30%
- PSEB Class 8 result 2025 declared: Check direct link to check, pass percentage and other details here
- Rajasthan Pashu Parichar result 2025 releasing today: Check steps to download and other key details here
- IPL Match Today, LSG vs MI: Dream 11 Team Prediction, head to head, key players, Ekana pitch, weather in Lucknow
- 49kg gold, Rs 38.4 crore in hawala transfers: How Karnataka jeweller Sahil Jain helped actor Ranya Rao
- Software engineer's salary dropped from Rs 5.5 lakh to Rs 20,000? Bombay HC calls it ‘unbelievable’, fines him Rs 1 lakh for not paying wife, kid maintenance
- In counter to Yunus's remark, PM Modi says Northeast integral to Bimstec
Visual Stories
- How to make South Indian Paneer Butter Masala Dosa for breakfast
- 10 ancient animals that still exist
- 10 exotic animals to spot inside Kashmir's Dachigam National Park
- 10 powerful ways to detox and reset your mind
- 10 things parents should never do in the morning before sending kids to school
TOP TRENDS
UP NEXT
Start a Conversation
Post comment