This story is from August 16, 2018
Green impact downplayed to fast-track housing plan?
NEW DELHI: While the
According to an environment ministry office memorandum (OM) of 2010, all inter-linked and integrated projects should have a common environment impact assessment (EIA).
But this appears to have been violated for the
One project, one green assessment
“Integrated and inter-linked projects having multi-sectoral components shall prepare a common EIA report, covering impact of each of the component in a comprehensive manner after obtaining terms of reference (TORs) from each of the sectoral expert appraisal committees (EACs),” states the OM, adding that after proposals relating to various components have been considered … these proposals will be processed on individual files for obtaining simultaneous approval of the competent authority.” This cumulative assessment hasn’t happened for the seven projects that submitted separate EIA reports and got environmental clearances separately.
Legal researchers Manju Menon and Kanchi Kohli point out that “EIA notification requires projects to reveal cumulative impacts with other existing or planned activities in the vicinity. These colonies comprise a contiguous area of 571 acres of government housing, north and south of the Ring Road near AIIMS. This region is one of Delhi’s best-kept landscapes.”
They said it would have been useful if the government engaged competent agencies to conduct a full geospatial survey and develop a detailed plan for the region, keeping in mind the multiple priorities of housing, hospitability and heritage in a growing city.
“This would have helped generate an integrated urban design before embarking on construction,” they said.
No certificate from NDMC on water supply, no traffic plan
But there are other discrepancies too. For example, when an application is made for environmental clearance, the environment ministry’s expert appraisal committee prepares terms of reference (TOR) for the project which need to be met or incorporated in the environment impact assessment report to be prepared by the project proponent.
In case of Netaji Nagar and Naoroji Nagar projects, however, some important conditions stipulated in the TOR were not incorporated in the EIA. The environment clearance was issued without these conditions being met. The Netaji Nagar GPRA TOR issued in August 2017 states that the project’s EIA should include an acceptance from NDMC on proposal to source water along with a certificate from NDMC showing they have a clearance from the Central Ground Water Authority for it.
It also said that a traffic impact analysis (TIA) shall be carried out, followed by a detailed traffic management plan approved by government agencies. Environmental clearance was granted to the project in November 2017 without NBCC submitting these conditional requirements.
“We find that the entire process of impact assessment and granting of environmental clearance is rushed. These important details are yet to be submitted and are not in public domain,” Kohli said.
The seven projects require about 15,799 kilo litres per day (KLD) of fresh water from NDMC and DJB. Even though this is a fraction of Delhi’s total water demand, experts seek clarity on how this will be sourced or rationed since Delhi is not able to meet its current water demand of 1,500 MGD — it supplies only 1,200 MGD.
‘No flora or fauna of ecological value’
The EIAs also ignore local biodiversity, say experts. For example, the Sarojini Nagar EIA states there are some trees on the “periphery” of the project site, “thorny bushes” and “no ecologically important flora or fauna species”. But Neha Sinha, wildlife conservationist who recently undertook a quick
redevelopment
of sevensouth Delhi colonies
was embroiled in controversy over a proposal to fell more than16
,000 trees,researchers
and residents have now found several otherlapses
in the way the projects’environmental impact
wasassessed
.But this appears to have been violated for the
seven
general pool residential accommodation (GPRA) projects being constructed.One project, one green assessment
“Integrated and inter-linked projects having multi-sectoral components shall prepare a common EIA report, covering impact of each of the component in a comprehensive manner after obtaining terms of reference (TORs) from each of the sectoral expert appraisal committees (EACs),” states the OM, adding that after proposals relating to various components have been considered … these proposals will be processed on individual files for obtaining simultaneous approval of the competent authority.” This cumulative assessment hasn’t happened for the seven projects that submitted separate EIA reports and got environmental clearances separately.
Legal researchers Manju Menon and Kanchi Kohli point out that “EIA notification requires projects to reveal cumulative impacts with other existing or planned activities in the vicinity. These colonies comprise a contiguous area of 571 acres of government housing, north and south of the Ring Road near AIIMS. This region is one of Delhi’s best-kept landscapes.”
“This would have helped generate an integrated urban design before embarking on construction,” they said.
No certificate from NDMC on water supply, no traffic plan
But there are other discrepancies too. For example, when an application is made for environmental clearance, the environment ministry’s expert appraisal committee prepares terms of reference (TOR) for the project which need to be met or incorporated in the environment impact assessment report to be prepared by the project proponent.
In case of Netaji Nagar and Naoroji Nagar projects, however, some important conditions stipulated in the TOR were not incorporated in the EIA. The environment clearance was issued without these conditions being met. The Netaji Nagar GPRA TOR issued in August 2017 states that the project’s EIA should include an acceptance from NDMC on proposal to source water along with a certificate from NDMC showing they have a clearance from the Central Ground Water Authority for it.
It also said that a traffic impact analysis (TIA) shall be carried out, followed by a detailed traffic management plan approved by government agencies. Environmental clearance was granted to the project in November 2017 without NBCC submitting these conditional requirements.
“We find that the entire process of impact assessment and granting of environmental clearance is rushed. These important details are yet to be submitted and are not in public domain,” Kohli said.
The seven projects require about 15,799 kilo litres per day (KLD) of fresh water from NDMC and DJB. Even though this is a fraction of Delhi’s total water demand, experts seek clarity on how this will be sourced or rationed since Delhi is not able to meet its current water demand of 1,500 MGD — it supplies only 1,200 MGD.
‘No flora or fauna of ecological value’
The EIAs also ignore local biodiversity, say experts. For example, the Sarojini Nagar EIA states there are some trees on the “periphery” of the project site, “thorny bushes” and “no ecologically important flora or fauna species”. But Neha Sinha, wildlife conservationist who recently undertook a quick
biodiversity
survey, found 26 bird species, 11 butterfly species and seven insect species.Popular from City
- Air India pilot suicide: Mumbai Police probe Aditya Pundit's deleted WhatsApp chats and video calls
- 13 flights cancelled at Chennai airport due to bad weather, operational reasons
- Cyclone Fengal likely to cross TN-Puducherry coasts on Saturday afternoon; will Chennai get heavy rain?
- Cyclone Fengal: Holiday announced for schools, colleges in Chennai and nearby districts on Saturday
- BJP wants Eknath Shinde as deputy chief minister of Maharashtra to project message of unity
end of article
Trending Stories
- Rob Gronkowski skips FOX Sunday after Terry Bradshaw’s apology to honor $16 Billion company commitment
- PAN 2.0: Will You Get A New PAN Card & Will Your Existing PAN Become Invalid? What’s Special About PAN With Enhanced QR Code? Top 10 Points Taxpayers Should Know
- IPL Auction 2025: Full country-wise list of sold players for all 10 IPL teams along with their base price and auctioned price
- India Q2 GDP Growth 2024 Live Updates: Indian economy likely slowed down in July-September quarter
- ED raids on Shilpa Shetty's husband Raj Kundra in money laundering probe linked to pornographic content production
- IPL Auction 2025: Full and final list of sold and unsold players across all teams
- 8 popular schools of Chandigarh one can consider for quality education
Visual Stories
- 5 fruits one can grow in the balcony garden with ease (and how)
- 10 lesser-known breakfast dishes from Maharashtra
- 7 best food for kids to improve brain power early on
- 10 habits of parents that raises well-behaved kids
- How to grow Peace lily at home and make it flower quickly
TOP TRENDS
UP NEXT
Start a Conversation
Post comment