Silkyara miracle: 17 days, 57 metres, 41 lives, 1 incredible rescue

Timeline of the various challenges faced by the evacuation teams and the evolving strategies deployed to free the trapped workers since the tunnel collapse at dawn on Diwali

Tired of too many ads?go ad free now
Also See: Uttarakhand Tunnel News

November 12 | Day 1

- Portion of tunnel collapses around 6am, trapping 41 workers
- Rescue operation starts, involving shotcreting of loose structures and excavation of debris over 57 metres

Day 2

Tired of too many ads?go ad free now
- 4-inch supply lifeline established to provide dry ration and maintain oxygen supply
- First communication with workers Shotcreting stops due to falling debris, injuring 2 workers

Day 3

Drilling begins with locally sourced auger machine to create escape passage through debris
Tired of too many ads?go ad free now

Day 4

- Drilling work halts due to slow performance of auger machine
- Advanced American auger machine airlifted from Delhi

Tired of too many ads?go ad free now
Day 5

- American machine starts drilling 900mm pipes into debris
- Workers protest against the slow pace of rescue operation

Day 6
Tired of too many ads?go ad free now

- Auger machine faces problems, cannot drill beyond 22 meters into debris
- Cracking sounds trigger fears of further collapse; drilling suspended

Day 7

Tired of too many ads?go ad free now
- PMO team reaches tunnel to review the operation
- Decision to pursue multiple options simultaneously, including vertical drilling and creating escape channels

Day 8

- Union minister Nitin Gadkari visits tunnel, meets family members of trapped workers
Tired of too many ads?go ad free now
- Rescue agencies pursue groundwork for a ?ve-pronged strategy

Day 9

- Major breakthrough: Additional supply lifeline with 6-inch pipe established
- Australian tunnel expert Arnold Dix arrives at tunnel
Tired of too many ads?go ad free now

Day 10

First visuals of trapped workers emerge via endoscopic camera pushed through pipe

Day 11
Tired of too many ads?go ad free now

- Drilled significantly, pushing escape passage pipes 45 meters into debris
- Trapped workers get first hot meals
- Auger machine hits iron girder

Day 12
Tired of too many ads?go ad free now

- Metal obstacle that stopped drilling cleared
- Auger machine resumes boring, but can only drill 1.8 meters more before hitting another hard object

Day 13

Tired of too many ads?go ad free now
Change in strategy to mixed approach: Workers remove debris manually to make way for auger machine

Day 14

US-made auger machine blades hit metal obstacle, get entangled in rubble

Tired of too many ads?go ad free now
Day 15

Army personnel (Madras Sappers regiment) brought in to remove auger blades from pipe

Day 16

Tired of too many ads?go ad free now
‘Rat-hole’ miners, specialised in small tunnel burrowing, manually dig through debris

November 28 | Day 17

- At 1.10pm, miners achieve crucial breakthrough 7.12pm: NDRF team and doctors enter 800mm pipe to reach trapped workers

Tired of too many ads?go ad free now
- 7.28pm: First trapped worker, Vijay Horo, wheeled out on stretcher through pipe. All the trapped workers pulled out safely soon after.


About the Author

TOI City Desk

The TOI City Desk is an indefatigable team of journalists dedicat... Read More
Continue Reading
Follow Us On Social Media
end of article
More Trending Stories
Visual Stories
More Visual Stories
UP NEXT
Do Not Sell Or Share My Personal Information