Flyover holdup has locals fuming at railway crossing
CHENNAI: A long delay in opening a road over-bridge (RoB) connecting
The highways department and Southern Railway have completed construction of the flyover between
“The government issued the order for the project in 2010 but the highways departments and the railways started work only in 2014,” said
He said officials had workmen place stone slabs and other obstacles at both ends of the overpass to ensure that motorists do not use the road. Motorists and other commuters now have to take a circuitous route of 12km to go from one side of the bridge to the other.
Former fish eries minister and DMK leader K P P Samy visited the site and urged the government to open the bridge at the earliest. He said if it failed to do so, his party would organise a protest.
Members of the Left parties also showed their displeasure by sticking posters on the finished RoB, stating that the delay in opening the bridge has severely affected workers employees of companies with offices in Manali and in localities further west and south of the city.
“Schoolchildren, office-goers and workers are put to trouble because the bridge is yet to be opened,”
Sumathi said schoolchildren from Thiruvottiyur have to walk via the 12-km route to Manali and, as a consequence, find it difficult to reach on time.
Manali
andThiruvottiyur
has local residents seething while waiting at the railway crossing it was supposed to allow them to vault over.Thiruvottiyur Basin Road
(Mattu Mandhai) and Manali at a cost of Rs 47 crore. sThe department and the railways planned the 550m-long and 13.2m-wide viaduct on what had been a longstanding demand from residents to help them avoid having to wait at the railway crossing and to prevent accidents at the spot. It has a median, crash barriers and footpaths.“The government issued the order for the project in 2010 but the highways departments and the railways started work only in 2014,” said
V Sampathraj
a resident of Theradi, Thiruvottiyur. “There were problems with land acquisition but now that the authorities have completed work on the bridge and it is ready for use, we cannot fathom why it is not open to the public.”He said officials had workmen place stone slabs and other obstacles at both ends of the overpass to ensure that motorists do not use the road. Motorists and other commuters now have to take a circuitous route of 12km to go from one side of the bridge to the other.
Former fish eries minister and DMK leader K P P Samy visited the site and urged the government to open the bridge at the earliest. He said if it failed to do so, his party would organise a protest.
Members of the Left parties also showed their displeasure by sticking posters on the finished RoB, stating that the delay in opening the bridge has severely affected workers employees of companies with offices in Manali and in localities further west and south of the city.
“Schoolchildren, office-goers and workers are put to trouble because the bridge is yet to be opened,”
Basin Road
resident P Sumathi said. “None of us know why there has been a long delay to inaugurate the bridge.”Popular from City
- Air India pilot suicide: Mumbai Police probe Aditya Pundit's deleted WhatsApp chats and video calls
- 13 flights cancelled at Chennai airport due to bad weather, operational reasons
- Cyclone Fengal likely to cross TN-Puducherry coasts on Saturday afternoon; will Chennai get heavy rain?
- Cyclone Fengal: Holiday announced for schools, colleges in Chennai and nearby districts on Saturday
- BJP wants Eknath Shinde as deputy chief minister of Maharashtra to project message of unity
end of article
Trending Stories
- Rob Gronkowski skips FOX Sunday after Terry Bradshaw’s apology to honor $16 Billion company commitment
- PAN 2.0: Will You Get A New PAN Card & Will Your Existing PAN Become Invalid? What’s Special About PAN With Enhanced QR Code? Top 10 Points Taxpayers Should Know
- IPL Auction 2025: Full country-wise list of sold players for all 10 IPL teams along with their base price and auctioned price
- India Q2 GDP Growth 2024 Live Updates: Indian economy likely slowed down in July-September quarter
- ED raids on Shilpa Shetty's husband Raj Kundra in money laundering probe linked to pornographic content production
- IPL Auction 2025: Full and final list of sold and unsold players across all teams
- 8 popular schools of Chandigarh one can consider for quality education
Visual Stories
- 5 fruits one can grow in the balcony garden with ease (and how)
- 10 lesser-known breakfast dishes from Maharashtra
- 7 best food for kids to improve brain power early on
- 10 habits of parents that raises well-behaved kids
- How to grow Peace lily at home and make it flower quickly
TOP TRENDS
UP NEXT
Start a Conversation
Post comment