New norms for NH & bridge works: Longer timelines, realistic deadlines
New Delhi: In a major change in policy, govt has increased the time allowed for construction of 6-10 km-long bridges across rivers such as Ganga and Brahmaputra to six years and for 2.5-6 km-long bridges on Mahanadi and Godavari to five years. The timelines have been revised from the current 24-30 months.
Similarly, the construction period has been fixed at two years for national highway projects costing up to Rs 500 crore, 30 months for Rs 500-1,500 crore projects, and three years for works costing over Rs 1,500 crore.
The change in the ‘normative construction period’ has been made after a gap of 13 years, learning from past experience of how the average time taken for completion of NH projects has been over four years against the standard timeline of 2.5-3 years. The revised timeline for construction will be applicable for all NH projects to be bid out from May 6.
In a circular, the road transport ministry said present guidelines — issued in 2013 — are derived from a legacy linear model that does not explicitly account for voluminous earthwork, leading to unrealistic construction period and resulting in additional cost and risk.
“Therefore, a need was felt to revise the existing guidelines based on scientific analysis, understanding of completed projects, and prescribe a realistic construction period for civil works at DPR and bid invitation stage,” the ministry said. It added that the new norm will improve predictability in completion of projects, reduce disputes, enhance value and quality of NHs, for realistic and bankable bids, better quality outcomes and improved investor confidence.
An additional six months time has been provisioned in the new norms for critical projects which involve multiple flyovers, tunnels or elevated structures. Similarly, an addition of 12 months has been provisioned for projects that involve cutting and slope stabilisation in hilly states.
Ready to Make a Smarter Property Decision? Build Your Legacy with TOI Homes.
The change in the ‘normative construction period’ has been made after a gap of 13 years, learning from past experience of how the average time taken for completion of NH projects has been over four years against the standard timeline of 2.5-3 years. The revised timeline for construction will be applicable for all NH projects to be bid out from May 6.
In a circular, the road transport ministry said present guidelines — issued in 2013 — are derived from a legacy linear model that does not explicitly account for voluminous earthwork, leading to unrealistic construction period and resulting in additional cost and risk.
“Therefore, a need was felt to revise the existing guidelines based on scientific analysis, understanding of completed projects, and prescribe a realistic construction period for civil works at DPR and bid invitation stage,” the ministry said. It added that the new norm will improve predictability in completion of projects, reduce disputes, enhance value and quality of NHs, for realistic and bankable bids, better quality outcomes and improved investor confidence.
An additional six months time has been provisioned in the new norms for critical projects which involve multiple flyovers, tunnels or elevated structures. Similarly, an addition of 12 months has been provisioned for projects that involve cutting and slope stabilisation in hilly states.
Ready to Make a Smarter Property Decision? Build Your Legacy with TOI Homes.
Popular from Business
- Tata Sons' new ventures may lose up to 29,000 crore, up to 5x of FY26 estimates; revamp plan likely by June
- Air India CEO resigns amid mounting losses
- Stock market today: Nifty50 trades above 22,900, Sensex remains flat as oil prices stay above $110
- Air India CEO Campbell Wilson resigns
- Oil prices rise as Trump’s Hormuz threat looms; WTI hits $113, Brent climbs to $110
end of article
Trending Stories
- US-Israel-Iran War News Live Updates: 6 children killed in US-Israeli strike on Tehran; mediators push for 45-day truce as Trump deadline looms
- NFL Trade Rumors: Buffalo Bills urged to pursue $132 million Pittsburgh Steelers star to to boost Josh Allen’s offense
- Karnataka 2nd PUC Results 2026 Date Time Live Updates: Result likely on this date, over 7.1 lakh students await announcement
- Gold, Silver Rate Today Live Updates: How much precious metals cost today and where are prices headed this week?
- Assembly Elections 2026 Live Updates: PM Modi hails Assam rally crowd's 'unprecedented energy', says it'll 'demoralise' Congress
- Soldier arrives at Louisiana base for training, ICE arrests his Honduran wife who was brought to US as toddler
- Why was Alberto Del Rio arrested? Former WWE superstar detained in Mexico
Featured in Business
- No personal oral hearing needed before labelling bank accounts as fraud: SC
- Top stocks to buy today: Stock market recommendations for April 7, 2026 - check list
- Centre doubles 5kg cylinder allocation to states as Iran war squeezes LPG supply; focus on migrant workers
- Stock market today: Nifty50 opens below 22,800, Sensex tumbles over 800 points
- Oil prices rise as Trump’s Hormuz threat looms; WTI hits $113, Brent climbs to $110
- Govt e-Marketplace reports 7.4% fall in transactions
Photostories
- 5 castles where people still live—and you can visit too
- Platinum vs Silver: What are the main differences?
- Baby names inspired by Lord Hanuman
- 8 famous foods that aren’t actually from the countries you think
- Why rotis turn soggy in casserole & 5 tips to keep them moisture-free
- 6 ultra-rare Bugatti models ever built
- 7 painting styles that elevate your home décor with a luxurious touch
- 4 Bhagavad Gita shlokas that help when life feels unfair
- No symptoms but real risk: How prediabetes and prehypertension progress silently, and what you can do today to prevent future health issues
- 7 vegetables to plant in April for a thriving summer harvest
Up Next
Start a Conversation
Post comment